The National Assembly has adopted the Law on Tendering or the Law on Public Procurement, which is expected to encourage a more competitive environment for government bid packages. Le Net and Thai Huynh Ngoc Kim Ngan at LNT & Partners take some highlights on the document, passed on November 26, on Vietnam Investment Review.
The National Assembly has adopted the Law on Tendering or the Law onPublic Procurement, which is expected to encourage a more competitiveenvironment for government bid packages. Le Net and Thai Huynh Ngoc KimNgan at LNT & Partners take some highlights on the document, passedon November 26, on Vietnam Investment Review.

TheLaw on Tendering will come into effect on July 1, 2014. Notable changesinclude the repealing of Section 1, Chapter VI of the Law onConstruction (N°16/2003/QH11) and Article 2 of the Law Amending andSupplementing a Number of Articles of the Law relating to CapitalConstruction Investment (N°38/2009/QH12). With these changes, the newlaw will resolve the overlaps between the Law on Tendering and otherlaws such as the Law on Construction.

Aimed ataddressing certain loopholes and issues related to the current legalframework on procurement, the new Law on Tendering was intended toprovide new provisions to clarify these issues. It devotes a separatechapter to each of the following subjects:

Selectionvia online or e-procurement mechanisms to help simplify the biddingprocess and implement legislative information disclosure requirementsfor better transparency throughout the bidding process and projectimplementation;

Several options, includingapplication of modified criteria (specifically on cost and contractorqualifications), in the evaluation of bidding dossiers by biddingorganisers; and

Involvement of foreign contractorsbeing made subject to two new conditions; namely, that they must (i)work in partnership with a Vietnamese company or sub-contract a localcompany; and (ii) employ only foreign workers when there are noqualified Vietnamese workers available for the project.

As such, the amended provisions are also designed to support localcontractors participating in international projects. In addition, theLaw on Tendering also includes many new terms and some new principlesthat aim to actively enhance competitiveness, decentralise publicprocurement and promote anti-corruption measures. It also introduces anew scope of application for official development assistance (ODA)projects. It is expected that the implementing regulations will rein inODA projects to a more efficient level. Ideally, the regulations aim todetermine the steps towards controlling procurement activities, ensuringfairness between the parties, and limiting corruption.

There are two examples where the Law on Tendering has proven its efficiency.

Total estimated costs and the procedure for bidding supplements

During the process of implementing the winning package, contractorsoften apply to adjust costs of the project scale related to the bid costadjustment. Actual evidence shows that many projects are won by bidsthat are deliberately lower, but which later apply for an adjustment inthe scale of investment leading to increased levels of investment.Therefore, this new regulation is intended to overcome this issue,through the appointment of sub-contractors via bidding. As a result,this regulation should contribute to restricting wastage of the statebudget.

Responsibility of competent persons in bidding and direct appointment of contractor

Regarding the determination of competent persons, the regulation asdescribed in Article 4(3) is a step forward. This allows quick decisionsto be made on small packages. To avoid the downside of this regulation,the responsibility of the authorised individual is clearly defined. As aresult, this restricts the abuse of power by an authorised individual,closes a loophole and creates a healthier bidding environment.

However, apart from progress on this issue, there remain a number ofpractical issues that should be supplemented and rectified in thedecrees implementing the law.

Broad definition of state capital

The provisions of the applicable object are always a matter ofcontroversy and present an interesting point. This law provides thatprocurement activities include “implementation of investment projectsdeveloped by organisations other than those specified in points a and bof this paragraph may use state capital, capital of state-ownedenterprises, 30 per cent or more or less than 30 per cent but more than500 billion VMD in total investment of the project be approved”.

Article 4(44), closely outlines the definition of “state capital”. Thelaw defines state capital to include both equity and loan capital forthe purposes of this provision, including capital of State-ownedenterprises or loans that are guaranteed by the state or secured againststate assets. Due to this broad definition, most private publicpartnership projects (PPP) may fall into the scope of this application,because most public infrastructure projects may require stateguarantees.

Consequently, the status of statecapital under this law poses a great challenge to the current legalframework. As a result, different types of “State capital” outside thetraditional meaning of “state capital” will be restricted. The broadapplication of this law may further delay the implementation of manyprojects to organise tendering, such as joint ventures between foreigninvestors and state owned enterprises, or PPP projects in which theState participates.

Race to the bottom

Time is not the only concern with the Law on Tendering. Quality isalso an issue because it could be compromised by cost. Assessmentmethodology bids as described in Article 38 (1) of the Law on Tenderingintroduced lowest cost methods. This method is commonly used in a numberof developing countries. However, in theory, businesses cannotsimultaneously meet the multiple requirements of better quality andcheaper prices. Regrettably, the new law still follows the “cheap price”approach, which may turn out to be expensive in the long run because oflow product quality.

The low price approach mayalso be paralysed by price adjustment provisions in the granting of theproject. We understand that an adjustment in prices is “unavoidable”because the country’s macro-economy is still unstable. However, theparticular price may be flexible, but the total price should be fixed,since all the risks, such as the escalating price of materials andlabour costs, should be taken into account in the bidding price from thestart. In reality, the adjustment of prices has led to the situationwhere the prices of all projects have been driven up to levels higherthan the bids with many contractors intentionally delaying theconstruction process to have the prices adjusted.

Managing direct appointment of contractors

The method for the direct appointment of contractors should reflectreal world practices but at the same time, promote openness,transparency and prevention of corruption in the bidding process. Thisis a significant change from the former Law on Tendering in that it nowprescribes fixed price, cost evaluation and technical and cost methods.

The consideration should also be made when addingprovisions that ensure objectivity, transparency, efficiency andlimiting of corruption to the lowest price method. For that purpose, thelaw provides that the direct appointment should be adopted in simple orsmall-scale cases. However, what packages should be deemed as simple orsmall-scale? The current regulations are quite unclear, leading toseveral interpretations and different applications. Therefore, thisshould be further considered when applied in reality.

In addition, this new regulation resolves situations where projectswin the bid but fail to meet their deadline because contractors lackcapacity (only winning the bid on the basis of lowest price alone). Theweight given to the lowest bid as a decisive factor and failing to takeinto account other factors, is a main cause for faulty and low qualityprojects. This new regulations also prove that selection of contractorsshould not only be based on the “lowest bid” but also take into accountcontractor capacity, qualifications and experience, and sources ofsupply. However, the regulations on evaluating contractors shouldfurther focus on contractor capacity because “quality of the project asthe first and foremost priority”.

Overall, there aremany positive improvements in the new Law on Tendering, and anintention to enhance investment efficiency and reduce corruption.-VNA

See more

A motorbike production line of Honda Vietnam — a Japanese company located in Phu Tho province. (Photo: VNA)

🌞 Phu Tho emerges as FDI magnet following mergence

In the first seven months of the year, Phu Tho attracted an impressive 651.7 million USD in foreign direct investment, including 35 newly licensed projects totaling 119 million USD in registered capital and 45 existing projects with an additional capital of 533 million USD.
Infraction levels will correspond to fines of 1-80 million VND, depending on the nature and number of invoicing violations. (Photo: vietnamfinance.vn)

✤ Maximum fine of 3,000 USD proposed for violating invoice regulations

Under a draft to amend and supplement the Government's Decree 125/2020/ND-CP on administrative sanctions for violations of tax and invoice regulations, the Ministry of Finance has proposed classifying the failure to issue invoices into five different levels. Infraction levels will correspond to fines of 1 million VND to 80 million VND, depending on the nature and number of invoicing violations.
At the strategic partnership signing ceremony between Sun PhuQuoc Airways and Amadeus. (Photo: Sun Group)

𒁃 Sun PhuQuoc Airways enters strategic partnership with Amadeus to build a five-star aviation technology ecosystem

A new airline developed and invested by Sun Group — has officially announced a strategic partnership with Amadeus IT Group (Amadeus), one of the world’s leading travel technology companies. This agreement not only lays the foundation for a modern digital infrastructure but also marks a pivotal step in SPA’s global expansion strategy, enabling the airline to access international distribution networks and reach customers worldwide.
A local resident makes a bank transfer using the Momo app. (Photo: VNA)

𝐆 Banks accelerate digitalisation, non-cash payments

Cashless payments are growing at an impressive rate, averaging 30–40% annually. Vietnam’s per capita cashless transaction volume now trails only China, with total value of 295.2 quadrillion VND (11.26 trillion USD), or 26 times of its GDP.
{dagathomo tructiep hôm nay}|{link ae888 city 165}|{dá gà thomo}|{trực tiếp đá gà thomo hom nay}|{sbobet asian handicap}| {trực tiếp đá gà hom nay}|{link ae888 tools}|{truc tiep da ga thom}|{link ae888}|{link ae888 đăng nhập}|{link ae888 188}|{link ae888 venus casino}|{ae961}|{cách trị mạt gà}|{chẵn lẻ momo 24/7}|