PM requests settlement of obstacles to expressway project in Mekong Delta

Prime Minister Pham Minh Chinh had a working session on July 13 with ministries and localities in the Mekong Delta to resolve obstacles and promote strategic transport infrastructure development, after concluding two fact-finding trips to expressway construction projects.
PM Pham Minh Chinh speaks at the meeting (Photo: VNA)
PM Pham Minh Chinh speaks at the meeting (Photo: VNA)

Can Tho (VNA) - Prime Minister Pham Minh Chinh had a working session on July 13 with ministries and localities in the Mekong Delta to resolve obstacles and promote strategic transport infrastructure development, after concluding two fact-finding trips to expressway construction projects.

This was the third meeting of the Government leader with ministers, secretaries of provincial party committees and chairpersons of 13 provinces and cities in the Mekong Delta on the issue.

According to reports, the Mekong Delta is currently implementing five key transport projects, including the eastern section of the North-South Expressway project from Can Tho to Ca Mau; Chau Doc-Can Tho-Soc Trang Expressway; Cao Lanh-An Huu Expressway; My An-Cao Lanh Expressway; and Ho Chi Minh Road project (11km Rach Soi-Ben Nhat section, and 41km Go Quạo-Vinh Thuan section).

To date, four out of five projects have completed investment procedures and are under construction and the My An-Cao Lanh Expressway is slated to start construction at the beginning of 2025.

Site clearance, one of the most important steps which could define progress and set the construction schedule, is nearly complete. However, if any issues are unresolved by the end of July 2024, it could affect the overall completion of the projects.

Intensive efforts are being made in construction, but the progress has not met the planned schedule, mainly due to a previous shortage of sand. Fortunately, the material supply has now been stable, with about 65 million cu.m guaranteed.

Highlighting some difficulties and proposals to promote project implementation, ministries, sectors and localities pledged to continue cooperation and support to ensure smooth project progress and achieve the set goals.

Concluding the conference, PM Chinh congratulated the 13 provinces and cities in the Mekong Delta for initially forming an expressway network after three years of active implementation, significantly developing the transport infrastructure in line with the strategic breakthrough spirit of the 13th National Party Congress' Resolution. Various modes of transportation have developed rapidly and comprehensively in the Mekong Delta.

On behalf of the Government, PM Chinh praised the efforts and dedication of ministries, sectors, localities, project management boards, companies, contractors, supervisory consultants and the team of officials, engineers, and workers who have been working diligently at the project sites.

He also thanked and praised the families, communities and individuals who supported and quickly handed over land for project construction.

The Government leader urged agencies and units, especially leaders, to prioritise national and ethnic interests, fulfill their responsibilities and have integrity, talent, responsibility and efficiency. Management must continuously be improved, practical, smart, digitalised and reduce administrative burdens and compliance costs for people and businesses.

He emphasised the goal of having 600km of expressways in the Mekong Delta by 2025 and 1,200km by 2030, assigning progress targets for each project, focusing on the North-South and East-West expressways.

The government leader requested ministries, sectors, and localities to thoroughly implement the principle of "only discussing actions, not setbacks", making all efforts to complete expressway projects on time, or ahead of schedule, which will open up new opportunities and development space for the entire Mekong Delta region, as well the country.

Construction must be conducted in the spirit of "persistence through rain or shine", "working day and night", "through holidays, through Tet, through weekends".

He urged mobilisation of the entire political system to participate in the 500-day campaign to complete 3,000km of expressways to celebrate the 50th anniversary of the Liberation of the South and reunification of the country, the 80th National Day, and the 14th National Party Congress.

Regarding capital, PM Chinh requested ministries and sectors to coordinate with localities to carefully calculate and report to competent authorities. The Ministry of Finance and the Ministry of Planning and Investment must advise and reasonably allocate funds and the Government will resolve issues within its authority.

Regarding site clearance, PM Chinh requested local secretaries and chairpersons to mobilise the combined strength of the entire political system to support project implementation, particularly relocating technical infrastructure, with a focus on resolving site clearance comprehensively to provide land for project construction.

He also ordered localities to take care of the lives of relocated households, ensuring that their conditions at new locations are equal to or better than before, focusing on employment and livelihoods, and ensuring the safety of people's lives and property during construction.

Regarding materials, he requested ensuring supply and completing on schedule. For sand fill materials, localities must actively enhance the mining capacity of material mines, transfer materials between projects to meet progress requirements and complete procedures for mining licences in July./.



VNA

See more

A motorbike production line of Honda Vietnam — a Japanese company located in Phu Tho province. (Photo: VNA)

꧟ Phu Tho emerges as FDI magnet following mergence

In the first seven months of the year, Phu Tho attracted an impressive 651.7 million USD in foreign direct investment, including 35 newly licensed projects totaling 119 million USD in registered capital and 45 existing projects with an additional capital of 533 million USD.
Infraction levels will correspond to fines of 1-80 million VND, depending on the nature and number of invoicing violations. (Photo: vietnamfinance.vn)

🌼 Maximum fine of 3,000 USD proposed for violating invoice regulations

Under a draft to amend and supplement the Government's Decree 125/2020/ND-CP on administrative sanctions for violations of tax and invoice regulations, the Ministry of Finance has proposed classifying the failure to issue invoices into five different levels. Infraction levels will correspond to fines of 1 million VND to 80 million VND, depending on the nature and number of invoicing violations.
At the strategic partnership signing ceremony between Sun PhuQuoc Airways and Amadeus. (Photo: Sun Group)

ಌ Sun PhuQuoc Airways enters strategic partnership with Amadeus to build a five-star aviation technology ecosystem

A new airline developed and invested by Sun Group — has officially announced a strategic partnership with Amadeus IT Group (Amadeus), one of the world’s leading travel technology companies. This agreement not only lays the foundation for a modern digital infrastructure but also marks a pivotal step in SPA’s global expansion strategy, enabling the airline to access international distribution networks and reach customers worldwide.
A local resident makes a bank transfer using the Momo app. (Photo: VNA)

ꦺ Banks accelerate digitalisation, non-cash payments

Cashless payments are growing at an impressive rate, averaging 30–40% annually. Vietnam’s per capita cashless transaction volume now trails only China, with total value of 295.2 quadrillion VND (11.26 trillion USD), or 26 times of its GDP.
{dagathomo tructiep hôm nay}|{link ae888 city 165}|{dá gà thomo}|{trực tiếp đá gà thomo hom nay}|{sbobet asian handicap}|