Infrastructure, planning and market keys to LNG power development

Infrastructure, planning and a market mechanism were among key issues that must be addressed in order to develop a market for liquefied natural gas (LNG) in Vietnam, heard participants at a conference on LNG on November 22 in Hanoi.
Infrastructure, planning and market keys to LNG power development ảnh 1Thi Vai Terminal, an LNG storage facility in the southern province of Ba Ria-Vung Tau. (Photo: VNA)

Hanoi (VNS/VNA) - Infrastructure, planning and amarket mechanism were among key issues that must be addressed in order todevelop a market for liquefied natural gas (LNG) in Vietnam, heardparticipants at a conference on LNG on November 22 in Hanoi. 

Deputyhead of the Electricity and Renewable Energy Department under the Ministry ofIndustry and Trade (MoIT) Bui Quoc Hung said the importation of LNG must followinternational trade standards and regulations while Vietnam is still lacking inmany key areas including design, construction, and operation of infrastructurefor LNG imports. 

As of now, the country has not yet developed a fully functional legal frameworkfor its LNG power projects. This is especially concerning as LNG prices haveseen significant fluctuations in recent years, which will likely hurtprice-sensitive markets such as Vietnam.

In addition, LNG power projects often require long-term commitments and aresubject to market changes and international geopolitical events. They alsooften demand an advanced level of technology and large capital investmentsby experienced and financially capable investors. 

Hung said the biggest challenge for LNG power projects, from an investor'sperspective, lies in negotiating Power Purchase Agreements (PPA), which must beconducted in accordance with the regulations of the MoIT. 

Industry experts said such projects will likely face fierce competition fromother power-generating plants, traditional and renewable, as the VietnameseGovernment does not offer guarantees for LNG. 

Deputy Director-General of PetroVietnam Gas (PV Gas) Huỳnh Quang Hai said oneof the most difficult challenges to overcome was a lack of centralised LNGstorage facility.

"The idea is to have multiple storages for LNG to supply multiple LNGpower plants but many localities still have no plans for warehouses andpipelines. It will be extremely challenging to meet the plants' demand withjust one warehouse," he said. 

Hai proposed having dedicated warehouses for each LNG power plant to bring downtransport costs and the construction of warehouse hubs and ports. He said theGovernment must quickly establish policies related to LNG projects, includingtransitioning prices, LNG purchase contracts and power purchase contracts. 

Economist Ngo Tri Long said pricing remains a key problem, holding back thedevelopment of an LNG market in Vietnam. 

He advised the Government to employ a market-oriented approach while trying tobalance the rights and interests of both investors and consumers. This isespecially important to LNG power projects as LNG import costs typically amountto 70-80% of its total costs.

He said Vietnam could consider setting up several specialised import hubs tosupply LNG power projects, which are under the management of the State, toensure transparency and compliance. 

He said the Government must select capable investors, offer additionalfinancial incentives, standardise technical and legal requirements to give themarket a boost. 

"It is unlikely LNG projects can proceed according to schedule and operateefficiently without a form of guarantee and successfully negotiated PPAs,"Long said. 

Economist Dinh Trong Thinh from the Vietnam Academy of Finance said LNG poweris to play a key part in meeting Vietnam’s energy target, which has beenprojected at 150.000-160.000MW in 2030 or double the country's current output.

In addition, as Vietnam remains committed to lowering its carbon emissions thecountry's power sector must maintain growth while going under a majorrestructuring process.

Under the National Power Plan VIII, LNG power was expected to increase from 7GW(10.2% of the total output) in 2020 to 32GW (21.8% of total output) in 2030. Hesaid LNG remains a viable option to make up for shortfalls from outputgenerated from renewable sources and a key component in ensuring Việt Nam'senergy security.

Nguyen HungDung, deputy chairman and secretary-general of the Vietnam PetroleumAssociation, said under the National Power Plan VIII there is only one1-million tonnes storage planned while many localities across the country havevoiced their interest in developing LNG.

ℱ "The sector's key issues remain profitability and the sustainabledevelopment of a strong and fair LNG market," he said./.

VNA

See more

A motorbike production line of Honda Vietnam — a Japanese company located in Phu Tho province. (Photo: VNA)

♋ Phu Tho emerges as FDI magnet following mergence

In the first seven months of the year, Phu Tho attracted an impressive 651.7 million USD in foreign direct investment, including 35 newly licensed projects totaling 119 million USD in registered capital and 45 existing projects with an additional capital of 533 million USD.
Infraction levels will correspond to fines of 1-80 million VND, depending on the nature and number of invoicing violations. (Photo: vietnamfinance.vn)

🎃 Maximum fine of 3,000 USD proposed for violating invoice regulations

Under a draft to amend and supplement the Government's Decree 125/2020/ND-CP on administrative sanctions for violations of tax and invoice regulations, the Ministry of Finance has proposed classifying the failure to issue invoices into five different levels. Infraction levels will correspond to fines of 1 million VND to 80 million VND, depending on the nature and number of invoicing violations.
At the strategic partnership signing ceremony between Sun PhuQuoc Airways and Amadeus. (Photo: Sun Group)

⭕ Sun PhuQuoc Airways enters strategic partnership with Amadeus to build a five-star aviation technology ecosystem

A new airline developed and invested by Sun Group — has officially announced a strategic partnership with Amadeus IT Group (Amadeus), one of the world’s leading travel technology companies. This agreement not only lays the foundation for a modern digital infrastructure but also marks a pivotal step in SPA’s global expansion strategy, enabling the airline to access international distribution networks and reach customers worldwide.
A local resident makes a bank transfer using the Momo app. (Photo: VNA)

𝔍 Banks accelerate digitalisation, non-cash payments

Cashless payments are growing at an impressive rate, averaging 30–40% annually. Vietnam’s per capita cashless transaction volume now trails only China, with total value of 295.2 quadrillion VND (11.26 trillion USD), or 26 times of its GDP.
{dagathomo tructiep hôm nay}|{link ae888 city 165}|{dá gà thomo}|{trực tiếp đá gà thomo hom nay}|{sbobet asian handicap}|