The Ho Chi Minh City Power Corporation plans to bury more than 1,000kmof electric lines and cables underground in 2014 and 2015, heard aconference reviewing the work in the southern hub on June 4.
From now to 2015, the firm will complete 36 ongoing projects installing 329km of power lines underground.
Itplans to start 42 projects burying 394km of wires in 2014 while another38 projects will begin in 2015 for 342km of power lines.
By theend of 2015, the city is expected to finish the rearrangement of 445kmof middle voltage and 691km of low voltage lines along with 11.7km of110kV cables.
The corporation attributed the great volume of work for 2014-2015 to the slow progress made from 2011 to 2013.
ViceChairman of the municipal People’s Committee Le Manh Ha said thatburying electricity wires and telecommunication cables underground hasgiven a facelift to the city.
However, to ensure the work’sfurther progress, the corporation and managerial agencies, such as themunicipal departments of transport, information and communications andindustry and trade, need to devise measures to tackle existing problems,he added.
Presently, the city has buried 28 percent of middlevoltage and 10.6 percent of low voltage lines. The respective figuresare expected to reach 30 percent and 20 percent in 2015.-VNA
From now to 2015, the firm will complete 36 ongoing projects installing 329km of power lines underground.
Itplans to start 42 projects burying 394km of wires in 2014 while another38 projects will begin in 2015 for 342km of power lines.
By theend of 2015, the city is expected to finish the rearrangement of 445kmof middle voltage and 691km of low voltage lines along with 11.7km of110kV cables.
The corporation attributed the great volume of work for 2014-2015 to the slow progress made from 2011 to 2013.
ViceChairman of the municipal People’s Committee Le Manh Ha said thatburying electricity wires and telecommunication cables underground hasgiven a facelift to the city.
However, to ensure the work’sfurther progress, the corporation and managerial agencies, such as themunicipal departments of transport, information and communications andindustry and trade, need to devise measures to tackle existing problems,he added.
Presently, the city has buried 28 percent of middlevoltage and 10.6 percent of low voltage lines. The respective figuresare expected to reach 30 percent and 20 percent in 2015.-VNA